The client required storage for chemical storage adjacent
to the existing plant.
Building
Size:
900 square
feet.
Time
to Complete:
From start of production to completion on site, 7 weeks.
Project
Outline:
This building was constructed in
two sections. Given the intended use, this building
features a welded structural steel containment floor
and a dry-chemical fire suppression system, and mechanical
ventilation. It has a standard electrical package consisting
of a 100 amp service panel, duplex receptacles and interior
mounted light fixtures with photocell control.