Security & Control

Project Summary #C01505:
Border Crossing Customs Booths, Peace Bridge, Fort Erie, Ontario
Client Need:

The client required a series of identical border crossing kiosks.

Building Size:
14 units of 40 square feet each.
Time to Complete:
From start of production to completion on site, 16 weeks.
Project Outline:

In conjunction with the Buffalo Fort Erie Peace Bridge Authority and Customs Canada, Canada Kiosk - an NRB company specializing in security, control and access-related solutions - designed 14 specialized inspection booths to exacting specifications. These booths were designed with the specific intent to maximize the comfort of the Customs Officer.

Features include welded steel frame construction, and green-tinted reflective glazing to minimize glare. A retractable green-tinted acrylic windbreak protects Customs Officers, and there is an exterior mounted radiant heater over the windows. The slider door features a full-lite slider window, providing flexibility of communication through the window with an easy exit from the booth to conduct inspections. There is a stainless steel work counter and storage drawer.

Download the project summary
(PDF 0.18 Mb)

Photo 2
Home Site Map

 Project Summaries
    Two Storey Control Station
    12 Border Crossing Customs      Booths
    14 Border Crossing Customs      Booths
    Two Storey, Elevated Control      Station
    Guard Houses

    Back to Building Lines
    Request Information CD

 

Contact NRB
Case Studies The NRB Total Building Experience spacer  
Privacy Policy        © 2007 NRB Inc